HSBC, Canary Wharf (Phase II), Construction began in January 1999 with the boring of the building’s substantial deep pile foundations. During spring, the concrete core rose steadily with approximately 100 workers on site each day, increasing monthly by several hundred to over 1000 at the end of 1999. The tower began to assume its current appearance in summer 2000 when work started on installing the 4900 glass panels.